[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-50853":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},50853,53,1,"单选题","在确定材料定额消耗量时，建筑工程必须消耗的材料不包括( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","不可避免的场外运输损耗材料",true,{"key":16,"text":17,"correct":18},"B","直接使用在工程上的材料",false,{"key":20,"text":21,"correct":18},"C","不可避免的施工废料",{"key":23,"text":24,"correct":18},"D","不可避免的场内运输损耗材料","材料消耗定额是指在合理和节约使用材料的条件下，生产单位合格产品所必须消耗的一定规格的材料、成品、半成品和水、电等资源的数量标准。编制材料消耗定额，主要包括确定直接使用在工程上的材料净用量和在施工现场内运输及操作过程中不可避免的废料和损耗。",{"id":6,"name":27,"category":28,"favorite":29},"(初级)建筑与房地产经济","经济金融",0]