[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-50848":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},50848,53,1,"单选题","下列工人工作时间中，属于损失时间的是( )。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","休息时间",false,{"key":16,"text":17,"correct":14},"B","不可避免中断时间",{"key":19,"text":20,"correct":14},"C","辅助工作时间",{"key":22,"text":23,"correct":24},"D","停工时间",true,"工人工作时间分为必要消耗时间和损失时间。必要消耗时间包括有效工作时间、休息和不可避免中断时间。损失时间包括多余和偶然时间、停工时间、违背劳动纪律损失时间。",{"id":6,"name":27,"category":28,"favorite":29},"(初级)建筑与房地产经济","经济金融",0]