[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-50737":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},50737,53,1,"单选题","在流水施工中，当每个施工过程在各个施工段上的流水节拍不尽相等，可以组织( )。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","全等节拍流水施工",false,{"key":16,"text":17,"correct":14},"B","异步距流水施工",{"key":19,"text":20,"correct":21},"C","分别流水施工",true,{"key":23,"text":24,"correct":14},"D","成倍节拍流水施工","在实际工作中，通常每个施工过程在各个施工段上的工程量彼此不相等，或各专业工作队的生产效率相差较大，导致多数流水节拍彼此不相等，可以采用分别流水施工。分别流水施工是指参加流水作业的各施工过程在各施工段上的流水节拍无特定规律的流水施工组织方式。",{"id":6,"name":27,"category":28,"favorite":29},"(初级)建筑与房地产经济","经济金融",0]