[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-50730":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},50730,53,1,"单选题","与网络图相比，横道图编制工程进度计划的优点是( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","能清楚地表达工作之间相互联系. 相互制约的关系",false,{"key":16,"text":17,"correct":18},"B","形象直观. 简单明了",true,{"key":20,"text":21,"correct":14},"C","可进行资源优化",{"key":23,"text":24,"correct":14},"D","可进行各种时间参数的计算，确定进度计划的关键线路","考核横道图编制工程进度计划的有点。",{"id":6,"name":27,"category":28,"favorite":29},"(初级)建筑与房地产经济","经济金融",0]