[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-50719":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},50719,53,1,"单选题","某分部工程可划分为甲、乙、丙三个施工过程，其流水节拍分别为6周、12周和9周，若组织成倍节拍流水施工，其流水步距和专业工作队总数应为( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","3周和3个",false,{"key":16,"text":17,"correct":18},"B","3周和9个",true,{"key":20,"text":21,"correct":14},"C","6周和3个",{"key":23,"text":24,"correct":14},"D","6周和9个","最大公约数为3，所以流水步距为3周。2+4+3=9。",{"id":6,"name":27,"category":28,"favorite":29},"(初级)建筑与房地产经济","经济金融",0]