[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-50710":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},50710,53,1,"单选题","某分部工程划分为甲、乙、丙三个施工过程，各施工过程的流水节拍分别为6周、8周和4周。若分为6个流水施工段组织成倍节拍流水施工，则其专业工作队总数和流水施工工期分别为（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","3队和18周",false,{"key":16,"text":17,"correct":14},"B","6队和24周",{"key":19,"text":20,"correct":21},"C","9队和28周",true,{"key":23,"text":24,"correct":14},"D","9队和34周","考核专业工作队总数和流水施工工期的计算。",{"id":6,"name":27,"category":28,"favorite":29},"(初级)建筑与房地产经济","经济金融",0]