[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-50699":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},50699,53,1,"单选题","工程进度计划的检查包括以下工作：①实际进度与计划进度的比较；②收集实际进度数据：③进度数据整理、统计和分析；④建立进度数据采集系统；⑤进度计划的调整；⑥进度偏差判定。各项工作之间的正确顺序是( )。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","①一②一③一④一⑤一⑥",false,{"key":16,"text":17,"correct":14},"B","②一③一④一①一⑤一⑥",{"key":19,"text":20,"correct":21},"C","④一②一③一①一⑥一⑤",true,{"key":23,"text":24,"correct":14},"D","③一②一①一④一⑥一⑤","考察工程项目进度计划的检查程序。",{"id":6,"name":27,"category":28,"favorite":29},"(初级)建筑与房地产经济","经济金融",0]