[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-50693":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},50693,53,1,"单选题","该工程的流水施工工期为( )天。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","15",false,{"key":16,"text":17,"correct":18},"B","27",true,{"key":20,"text":21,"correct":14},"C","30",{"key":23,"text":24,"correct":14},"D","36","计算施工工期：T=(m+N-1)×K=(5+5-1)*3=27(周)",{"id":6,"name":27,"category":28,"favorite":29},"(初级)建筑与房地产经济","经济金融",0]