[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-50690":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},50690,53,1,"单选题","该工程的流水施工段数应划分为( )。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","3",false,{"key":16,"text":17,"correct":14},"B","4",{"key":19,"text":20,"correct":21},"C","5",true,{"key":23,"text":24,"correct":14},"D","6","①确定流水步距K为各流水节拍的最大公约数，即K=3天。②由公式 b1=6\u002F3 =2, b2=6\u002F3 =2, b3=3\u002F3=1。③确定参加流水作业的专业工作队数 N=2+2+1=5(队)。 ④确定施工段数，取：m=5段。",{"id":6,"name":27,"category":28,"favorite":29},"(初级)建筑与房地产经济","经济金融",0]