[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-50687":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},50687,53,1,"单选题","制定工程项目成本改进措施要( )。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","面面俱到",false,{"key":16,"text":17,"correct":14},"B","全面铺开",{"key":19,"text":20,"correct":21},"C","抓住主要矛盾",true,{"key":23,"text":24,"correct":14},"D","抓住所有矛盾","成本分析要在“量化”分析的基础上，找出影响成本的原因，既要有主要原因，也要有次要原因，特别是主要原因要分析透彻，抓住主要矛盾，制定改进成本的措施。制定的成本改进措施要有针对性，要具体，要落实到人头。抓不住主要矛盾，制定的措施必然显得空洞，变成几条“放之四海而皆准”的措施。",{"id":6,"name":27,"category":28,"favorite":29},"(初级)建筑与房地产经济","经济金融",0]