[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-50673":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},50673,53,1,"单选题","某工程项目的装饰工程可以分解为 A、 B、 C、D四个施工过程，施工中分五个施工段组织流水作业，各施工过程的流水节拍均为3天，其中 C、D工作之间有2天技术间歇时间，则其流水施工工期为( )天。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","22",false,{"key":16,"text":17,"correct":14},"B","24",{"key":19,"text":20,"correct":21},"C","26",true,{"key":23,"text":24,"correct":14},"D","28","m=5,n=4,T=(5+4-1)*3+2=26",{"id":6,"name":27,"category":28,"favorite":29},"(初级)建筑与房地产经济","经济金融",0]