[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-50579":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},50579,53,1,"单选题","工程项目决策阶段管理工作的主要任务是( )。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","编制设计任务书",false,{"key":16,"text":17,"correct":14},"B","完成初步设计",{"key":19,"text":20,"correct":21},"C","确定项目的定义",true,{"key":23,"text":24,"correct":14},"D","组织工程招标","工程项目决策阶段管理工作的主要任务是确定项目的定义，项目实施阶段项目管理的主要任务是通过管理使项目的目标得以实现。",{"id":6,"name":27,"category":28,"favorite":29},"(初级)建筑与房地产经济","经济金融",0]