[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-50284":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},50284,53,1,"单选题","工程成本管理中将实际成本与预算成本的差额称为()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","项目成本降低额",false,{"key":16,"text":17,"correct":14},"B","管理成本降低额",{"key":19,"text":20,"correct":21},"C","实际成本降低额",true,{"key":23,"text":24,"correct":14},"D","计划成本降低额","重点区分概念。实际成本与预算成本的差额，称为实际成本降低额，实际成本降低额与预算成本的比率，称为实际成本降低率，都是企业综合收益水平的反映。计划成本与实际成本的差额称为项目成本降低额，项目成本降低额与计划成本的比率，称为项目成本降低率，都是考核项目成本目标的依据。",{"id":6,"name":27,"category":28,"favorite":29},"(初级)建筑与房地产经济","经济金融",0]