[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-50275":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},50275,53,1,"单选题","工程直接成本是指施工过程中直接耗费的()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","构成工程实体的各项支出",false,{"key":16,"text":17,"correct":14},"B","有助于工程形成的各项支出",{"key":19,"text":20,"correct":14},"C","构成工程实体和部分有助于工程形成的各项支出",{"key":22,"text":23,"correct":24},"D","构成工程实体或有助于工程形成的各项支出",true,"工程直接成本是指施工过程中直接耗费的构成工程实体或有助于工程形成的各项支出，包括人工费、材料费、机械使用费和其他直接费。",{"id":6,"name":27,"category":28,"favorite":29},"(初级)建筑与房地产经济","经济金融",0]