[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-50260":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},50260,53,1,"单选题","以工程成本发生时间划分的成本形式是()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","项目工程成本和企业工程成本",false,{"key":16,"text":17,"correct":14},"B","直接成本和间接成本",{"key":19,"text":20,"correct":14},"C","固定成本和变动成本",{"key":22,"text":23,"correct":24},"D","预算成本、计划成本和实际成本",true,"为适应工程成本管理的要求，工程成本以发生时间划分为预算成本、计划成本和实际成本。",{"id":6,"name":27,"category":28,"favorite":29},"(初级)建筑与房地产经济","经济金融",0]