[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-50232":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},50232,53,1,"单选题","根据历史成本的间接费用支出，结合压缩费用措施，可测算工程项目的()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","直接成本",false,{"key":16,"text":17,"correct":18},"B","间接成本",true,{"key":20,"text":21,"correct":14},"C","实际成本",{"key":23,"text":24,"correct":14},"D","计划成本","工程项目施工成本计划编制方法：①人工费的计划成本编制；②料费的计划成本编制；③机械费的计划成本编制；④其他直接费的计划成本编制；⑤间接成本的计划成本编制；⑥提出成本计划控制指标，落实到责任单位；⑦编制分管的成本费用支出预算。其中，材料费的计划成本编制由工程项目财务核算部门根据历史成本的间接费用支出以及压缩费用措施进行测算，填制间接成本计划表。",{"id":6,"name":27,"category":28,"favorite":29},"(初级)建筑与房地产经济","经济金融",0]