[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-50230":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},50230,53,1,"单选题","采用“按实计算分级编制”方法编制工程项目施工成本计划时，应首先要求成本责任部门或岗位提出()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","分管成本项目的降低成本计划",true,{"key":16,"text":17,"correct":18},"B","分管成本项目的资金计划",false,{"key":20,"text":21,"correct":18},"C","分部分项工程的降低成本计划",{"key":23,"text":24,"correct":18},"D","分部分项工程的资金计划","工程项目施工成本计划编制方法有很多，题干所说的按实计算分级编制的方法，即先由各成本责任部门或岗位提出分管成本项目的降低成本计划，再汇总编制全工程项目的施工成本计划。具体内容为：①人工费的计划成本编制；②料费的计划成本编制；③机械费的计划成本编制；④其他直接费的计划成本编制；⑤间接成本的计划成本编制；⑥提出成本计划控制指标，落实到责任单位；⑦编制分管的成本费用支出预算。",{"id":6,"name":27,"category":28,"favorite":29},"(初级)建筑与房地产经济","经济金融",0]