[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-50223":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},50223,53,1,"单选题","某施工企业购置了一台塔式起重机。关于该笔固定资产支出处理方式的说法，正确的是（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","可以一次性列入企业成本",false,{"key":16,"text":17,"correct":14},"B","可以一次性列入期间成本",{"key":19,"text":20,"correct":21},"C","不得一次性列入工程成本",true,{"key":23,"text":24,"correct":14},"D","可以部分列入期间成本","应当指出，企业下列支出不得列入工程成本，也不能列入企业成本：为购置和建造固定资产、无形资产和其他资产的支出；对外投资的支出；没收的财物、支付的滞纳金、罚款、违约金、赔偿金，以及企业赞助、捐赠支出，国家法律、法规规定以外的各种付费和国家规定不得列入成本费用的其他支出。",{"id":6,"name":27,"category":28,"favorite":29},"(初级)建筑与房地产经济","经济金融",0]