[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-50221":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},50221,53,1,"单选题","材料二次搬运费属于（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","材料费",false,{"key":16,"text":17,"correct":18},"B","其他直接费",true,{"key":20,"text":21,"correct":14},"C","直接费",{"key":23,"text":24,"correct":14},"D","间接费","其他直接费指不包括在人工费、材料费、机械使用费三种费用以内的施工现场发生的材料二次搬运费、临时设施摊销费、冬雨季施工增加费、工程定位复测费、工程点交费、场地清理费、生产工具用具使用费、检验试验费等。",{"id":6,"name":27,"category":28,"favorite":29},"(初级)建筑与房地产经济","经济金融",0]