[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-50210":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},50210,53,1,"单选题","影响工程成本的因素不包括()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","工程质量",true,{"key":16,"text":17,"correct":18},"B","完成单位工程量的物资和活劳动消耗数量",false,{"key":20,"text":21,"correct":18},"C","物资和活劳动的单价",{"key":23,"text":24,"correct":18},"D","工程量","影响工程成本的因素不论直接成本还是间接成本，归纳起来主要有以下三类因素：①工程量；②完成单位工程量的物资和活劳动消耗数量；③物资和活劳动的单价。",{"id":6,"name":27,"category":28,"favorite":29},"(初级)建筑与房地产经济","经济金融",0]