[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-50209":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},50209,53,1,"单选题","工程成本管理的环节包括()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","预测、计划和控制",false,{"key":16,"text":17,"correct":14},"B","预测、计划、控制和核算",{"key":19,"text":20,"correct":14},"C","预测、计划、控制、核算和分析",{"key":22,"text":23,"correct":24},"D","预测、计划、控制、核算、分析和考核",true,"施工项目成本管理的一般程序如下：①工程成本预测；②工程成本计划；③工程成本控制；④工程成本核算；⑤工程成本分析；⑥工程成本考核。工程成本管理的每一个环节都是相互联系和相互作用的。成本预测是成本决策的前提，成本计划是成本决策所确定目标的具体化。",{"id":6,"name":27,"category":28,"favorite":29},"(初级)建筑与房地产经济","经济金融",0]