[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-50187":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},50187,53,1,"单选题","某工程人工费结算收入为84万元，实际支出为91万元，则人工成本降低率为( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","7．69％",false,{"key":16,"text":17,"correct":18},"B","8．33％",true,{"key":20,"text":21,"correct":14},"C","7．89％",{"key":23,"text":24,"correct":14},"D","9．33％","考查工程成本分析的常用方法。 人工成本降低率=(结算收入-实际支出)／结算收入 根据公式，人工成本降低率=(84-91)／84=-8.33％。",{"id":6,"name":27,"category":28,"favorite":29},"(初级)建筑与房地产经济","经济金融",0]