[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-50137":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},50137,53,1,"单选题","关于合同价款约定一般规定的说法，正确的是( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","实行工程量清单计价的工程应采用单价合同",true,{"key":16,"text":17,"correct":18},"B","招标文件与中标人投标文件不一致的地方应以招标文件为准",false,{"key":20,"text":21,"correct":18},"C","实行工程量清单计价的工程应采用总价合同",{"key":23,"text":24,"correct":18},"D","实行工程量清单计价的工程应采用成本加酬金合同","实行工程量清单计价的工程应采用单价合同；招标文件与中标人投标文件不一致的地方应以投标文件为准。",{"id":6,"name":27,"category":28,"favorite":29},"(初级)建筑与房地产经济","经济金融",0]