[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-50122":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},50122,53,1,"单选题","根据《建设工程工程量清单计价规范》，对任一招标工程量清单项目，如果因工程量偏差和工程量变更等原因导致工程量偏差超过5%，且不超过15%时，应( )。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","调整其综合单价",false,{"key":16,"text":17,"correct":14},"B","调整其措施费",{"key":19,"text":20,"correct":21},"C","执行原有的综合单价",true,{"key":23,"text":24,"correct":14},"D","调整其他项目费","对任一招标工程量清单项目，如果因工程量偏差和工程量变更等原因导致工程量偏差超过15%时，可进行调整。",{"id":6,"name":27,"category":28,"favorite":29},"(初级)建筑与房地产经济","经济金融",0]