[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-50114":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},50114,53,1,"单选题","工程量清单计价模式下的工程费用包括分部分项工程费、措施项目费、其他项目费和()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","管理费、税金",false,{"key":16,"text":17,"correct":14},"B","材料费、规费",{"key":19,"text":20,"correct":21},"C","规费、税金",true,{"key":23,"text":24,"correct":14},"D","管理费、规费","工程量清单是表现拟建工程的分部分项工程项目、措施项目、其他项目、规费项目和税金项目的名称和相应数量的明细清单。",{"id":6,"name":27,"category":28,"favorite":29},"(初级)建筑与房地产经济","经济金融",0]