[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-50109":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},50109,53,1,"单选题","为完成工程项目施工，发生于该工程施工准备和施工过程中的技术、生活、安全、环境保护等方面的非工程实体项目是()项目。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","措施",true,{"key":16,"text":17,"correct":18},"B","其他",false,{"key":20,"text":21,"correct":18},"C","补充",{"key":23,"text":24,"correct":18},"D","规费","措施项目是指为完成工程项目施工，发生于该工程施工准备和施工过程中的技术、生活、安全、环境保护等方面的非工程实体项目。措施项目清单的编制应依据拟建工程的施工组织设计、拟建工程的施工技术方案、与拟建工程相关的工程施工规范与工程验收规范、招标文件及设计文件等。",{"id":6,"name":27,"category":28,"favorite":29},"(初级)建筑与房地产经济","经济金融",0]