[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-50059":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},50059,53,1,"单选题","材料从工地仓库、现场集中堆放地点或现场加工地点至操作地点的水平和垂直运输，所需的费用()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","包括在二次搬运费中",false,{"key":16,"text":17,"correct":18},"B","包括在材料消耗定额",true,{"key":20,"text":21,"correct":14},"C","按实际发生金额计人工程造价",{"key":23,"text":24,"correct":14},"D","不能计入工程造价","材料消耗定额，主要包括确定直接使用在工程上的材料净用量和在施工现场内运输及操作过程中的不可避免的废料和损耗。。",{"id":6,"name":27,"category":28,"favorite":29},"(初级)建筑与房地产经济","经济金融",0]