[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-50030":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},50030,53,1,"单选题","下列对预算定额的描述中，正确的是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","预算定额是计价定额",true,{"key":16,"text":17,"correct":18},"B","预算定额是直接用于施工管理中的定额",false,{"key":20,"text":21,"correct":18},"C","预算定额是初步设计阶段编制的定额",{"key":23,"text":24,"correct":18},"D","预算定额是在概算定额的基础上综合而成的","预算定额是规定一定计量单位的分项工程或结构构件所必须消耗的人工、材料和机械台班的数量标准，是计价定额。其主要是为了满足编制施工图的要求，是计算建筑安装产品价格的基础。选项C，不是预算定额，而是概算定额；选项D将两者关系颠倒，应该是“概算定额是在预算定额的基础上综合而成的”。",{"id":6,"name":27,"category":28,"favorite":29},"(初级)建筑与房地产经济","经济金融",0]