[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-49901":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},49901,53,1,"单选题","施工过程中工序质量监控的对象是（）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","工序能力指数",false,{"key":16,"text":17,"correct":14},"B","工程审图质量",{"key":19,"text":20,"correct":14},"C","工程监理活动",{"key":22,"text":23,"correct":24},"D","质量影响因素",true,"工序质量包含两个相互关联的内容，一是工序活动条件的质量，即每道工序投入的人力、材料、机械设备、方法和环境是否符合要求。二是工序活动效果的质量，即每道工序施工完成的工程产品是否达到有关质量标准。工序质量监控的对象是影响工序质量的因素，特别是对主导因素的监控，其核心是管因素、管过程，而不单纯是管结果。",{"id":6,"name":27,"category":28,"favorite":29},"(初级)建筑与房地产经济","经济金融",0]