[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-49833":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},49833,53,1,"单选题","工程项目进度计划检查工作的主要内容包括：1实际进度与计划进度的比较；2收集实际进度数据；3数据整理、统计、分析；4建立进度数据采集系统；5进度计划的调整。其正确的开展顺序是（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","1-3-4-2-5",false,{"key":16,"text":17,"correct":14},"B","4-3-2-1-5",{"key":19,"text":20,"correct":21},"C","4-2-3-1-5",true,{"key":23,"text":24,"correct":14},"D","2-4-3-1-5","根据教材表4—13工程项目进度计划得到检查程序来做此题。",{"id":6,"name":27,"category":28,"favorite":29},"(初级)建筑与房地产经济","经济金融",0]