[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-49826":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},49826,53,1,"单选题","某工程项目的基础工程可以分解为甲、乙、丙、丁四个施工过程，各施工过程的流水节拍均为3周，分4个施工段组织流水作业，则其流水施工工期是()周。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","15",false,{"key":16,"text":17,"correct":14},"B","17",{"key":19,"text":20,"correct":14},"C","19",{"key":22,"text":23,"correct":24},"D","21",true,"m=4,n=4,t=3,T=(m+n-1)*t=(4+4-1)*3=21",{"id":6,"name":27,"category":28,"favorite":29},"(初级)建筑与房地产经济","经济金融",0]