[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-49817":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},49817,53,1,"单选题","某4人专业工作队完成一工作量为100的施工段，当每一工日完成的计划产量为5时，其流水节拍为()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","25",false,{"key":16,"text":17,"correct":14},"B","20",{"key":19,"text":20,"correct":14},"C","10",{"key":22,"text":23,"correct":24},"D","5",true,"流水节拍是指某一个专业工作队在一个施工段上完成一个施工过程的持续时间。式中，t表示流水节拍，Q表示某施工段的工程量，R表示专业工作队的人数或机械台数，S表示产量定额，单位时间完成的工程量。 t=Q\u002FRS=100\u002F（4*5）=5",{"id":6,"name":27,"category":28,"favorite":29},"(初级)建筑与房地产经济","经济金融",0]