[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-49807":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},49807,53,1,"单选题","工程项目施工可以采用不同的组织方式，其中有利于资源均衡使用的组织方式是（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","依次施工",false,{"key":16,"text":17,"correct":14},"B","平行施工",{"key":19,"text":20,"correct":21},"C","流水施工",true,{"key":23,"text":24,"correct":14},"D","搭接施工","流水施工是将拟建工程项目的施工对象分解为若干施工过程，并按照施工过程组建相应的专业工作队，各专业队伍按照施工顺序依次完成各个施工对象的施工过程，同时保证施工在时间和空间上连续、均衡、有节奏地进行，并使相邻的两个专业工作队能最大限度地搭接施工。",{"id":6,"name":27,"category":28,"favorite":29},"(初级)建筑与房地产经济","经济金融",0]