[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-49805":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},49805,53,1,"单选题","某工程项目基础工程和主体工程均可分为四段组织流水作业，其流水节拍分别为3、4、3、2周和4、2、4、3周，则两分部工程之间的流水步距及其流水施工工期为()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","4周和13周",false,{"key":16,"text":17,"correct":18},"B","4周和17周",true,{"key":20,"text":21,"correct":14},"C","3周和16周",{"key":23,"text":24,"correct":14},"D","3周和25周","根据上述条件，本工程宜组织分别流水施工。各施工过程流水节拍的累加数据系列：基础工程：3、7、10、12；主体工程：4、6、10、13。将两个施工过程的累加数据系列错位相减得：3、3、4、2、-13；流水步距等于各累加数据系列错位相减所得差值中数值最大者，即：K=Max(3 3 4 2 -13)=4(周)。流水施工工期：4+(4+2+4+3)=17(周)。",{"id":6,"name":27,"category":28,"favorite":29},"(初级)建筑与房地产经济","经济金融",0]