[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-49803":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},49803,53,1,"单选题","组织流水施工可以节省工作时间，其所用的手段是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","连续施工",false,{"key":16,"text":17,"correct":18},"B","搭接施工",true,{"key":20,"text":21,"correct":14},"C","依次施工",{"key":23,"text":24,"correct":14},"D","动态施工","流水施工可以保证各专业队伍施工在时间和空间上连续、均衡、有节奏地进行，专业队伍按照施工顺序依次完成各个施工对象的施工过程，同时并使相邻的两个专业工作队能最大限度地搭接施工。",{"id":6,"name":27,"category":28,"favorite":29},"(初级)建筑与房地产经济","经济金融",0]