[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-49795":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},49795,53,1,"单选题","为确保建设工程进度控制目标的实现，必须认真制定进度管理的有关措施。下列各项进度管理措施中，属于技术措施的是（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","编制进度计划和进度控制的工作流程",false,{"key":16,"text":17,"correct":14},"B","对应急赶工给予相应的赶工费用补偿",{"key":19,"text":20,"correct":21},"C","选择对实现进度目标有利的设计方案",true,{"key":23,"text":24,"correct":14},"D","推行CM承发包模式，并协调合同工期与进度计划之间的关系","A选项属于组织措施；B选项属于经济措施；D选项属于合同措施。分析影响进度目标实现的干扰和风险因素属于组织措施，而加强工程风险管理与索赔管理属于合同措施。",{"id":6,"name":27,"category":28,"favorite":29},"(初级)建筑与房地产经济","经济金融",0]