[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-49793":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},49793,53,1,"单选题","收集工程实际进度的有关数据、资料，经加工整理后与计划进度进行比较，提供进度比较分析报告，这是进度管理措施中的()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","组织措施",false,{"key":16,"text":17,"correct":14},"B","技术措施",{"key":19,"text":20,"correct":21},"C","信息管理措施",true,{"key":23,"text":24,"correct":14},"D","经济措施","信息管理措施主要包括：建立进度信息收集和报告制度，即通过收集工程实际进度的有关数据、资料，经加工整理后与计划进度进行比较，及时提供进度比较分析报告，为计划的检查和调整提供依据，从而提高进度信息处理的效率、促进进度信息的交流和项目各参与方协同作业。",{"id":6,"name":27,"category":28,"favorite":29},"(初级)建筑与房地产经济","经济金融",0]