[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-49791":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},49791,53,1,"单选题","工程进度管理的主要环节是工程进度计划的()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","编制和优化",false,{"key":16,"text":17,"correct":18},"B","编制和实施控制",true,{"key":20,"text":21,"correct":14},"C","实施和检查",{"key":23,"text":24,"correct":14},"D","检查和纠偏","工程进度管理主要包括工程项目进度计划的编制和进度计划的实施控制两大环节，其主要工作过程为：确定进度目标、编制进度计划--实施进度计划--进度状况检查--分析、处理偏差等基本过程。",{"id":6,"name":27,"category":28,"favorite":29},"(初级)建筑与房地产经济","经济金融",0]