[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-49788":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},49788,53,1,"单选题","某工程项目基础工程和主体工程均可分为三段组织流水作业，其流水节拍分别为3周、3周、4周和2周、3周、3周，则该两分部工程之间的流水步距及其流水施工工期分别是()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","3周和11周",false,{"key":16,"text":17,"correct":14},"B","3周和18周",{"key":19,"text":20,"correct":21},"C","5周和13周",true,{"key":23,"text":24,"correct":14},"D","5周和15周","本题采用分别流水施工方法求解。流水步距为：5，工期为：5+（2+3+3)=13",{"id":6,"name":27,"category":28,"favorite":29},"(初级)建筑与房地产经济","经济金融",0]