[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-49786":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},49786,53,1,"单选题","下列有关分别流水施工的说法中，正确的是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","组织分别流水施工时各个施工段上均无空闲",false,{"key":16,"text":17,"correct":18},"B","确定各施工过程相邻两个专业工作队之间的流水步距是组织分别流水施工的关键步骤",true,{"key":20,"text":21,"correct":14},"C","相邻施工过程之间的流水步距为常数",{"key":23,"text":24,"correct":14},"D","流水节拍较长的施工过程需要组织多个专业队伍","组织分别流水施工的关键步骤是确定各施工过程相邻两个专业工作队之间的流水步距。",{"id":6,"name":27,"category":28,"favorite":29},"(初级)建筑与房地产经济","经济金融",0]