[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-49783":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},49783,53,1,"单选题","某分部工程可划分为 A、 B、C三个施工过程，其流水节拍分别为8天、12天和4天。若组织成倍节拍流水施工，其流水步距和专业工作队总数应分别是()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","2天和3个",false,{"key":16,"text":17,"correct":14},"B","4天和3个",{"key":19,"text":20,"correct":21},"C","4天和6个",true,{"key":23,"text":24,"correct":14},"D","2天和12个","流水节拍的最大公约数为：4，则专业工作队数为：2+3+1=6。",{"id":6,"name":27,"category":28,"favorite":29},"(初级)建筑与房地产经济","经济金融",0]