[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-49779":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},49779,53,1,"单选题","某分部工程有两个施工过程，其流水节拍分别为3、4、3、3天和2、5、4、3天，若该分部工程分为4个施工段组织流水作业，则其流水步距和流水施工工期分别为()天。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","3和16",false,{"key":16,"text":17,"correct":14},"B","3和17",{"key":19,"text":20,"correct":14},"C","5和18",{"key":22,"text":23,"correct":24},"D","5和19",true,"分别流水施工组织计算过程：①各施工过程流水节拍的累加数据系列，(3 710 13)和(2 7 11 14)；②相邻两个施工过程的累加数据系列错位相减，(3 5 3 2 -14)；③流水步距等于各累加数据系列错位相减所得差值中数值最大者，K=5；④计算流水施工工期，T=5+2+5+4+3=19。",{"id":6,"name":27,"category":28,"favorite":29},"(初级)建筑与房地产经济","经济金融",0]