[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-49774":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},49774,53,1,"单选题","流水施工中的工艺参数是指参与流水施工的()数目。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","施工",false,{"key":16,"text":17,"correct":14},"B","施工层",{"key":19,"text":20,"correct":21},"C","施工过程",true,{"key":23,"text":24,"correct":14},"D","工作队","组织流水施工时，首先应将工程对象划分为若干个施工过程。工艺参数是指参与流水施工的施工过程数目，一般用“n”表示。在划分施工过程时，只有那些对工程施工有直接影响的施工内容才予以考虑。",{"id":6,"name":27,"category":28,"favorite":29},"(初级)建筑与房地产经济","经济金融",0]