[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-49772":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},49772,53,1,"单选题","某现浇钢筋混凝土工程，由绑扎钢筋、安装模板和浇混凝土三个施工过程组成，其对应流水节拍分别为6周、12周和9周。若组织成倍节拍流水施工，其流水步距和专业工作队总数分别应为()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","3周和3个",false,{"key":16,"text":17,"correct":14},"B","6周和3个",{"key":19,"text":20,"correct":21},"C","3周和9个",true,{"key":23,"text":24,"correct":14},"D","6周和9个","流水步距K，为各施工过程的流水节拍的最大公约数，K=3。b1=6／3=2，b2=12／3=4，b3=9／3=3，参加流水作业的专业工作队数N=2+4+3=9。",{"id":6,"name":27,"category":28,"favorite":29},"(初级)建筑与房地产经济","经济金融",0]