[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-49769":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},49769,53,1,"单选题","全等节拍和成倍节拍流水施工组织的第一项工作是()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","确定施工起点流向，划分施工段",false,{"key":16,"text":17,"correct":14},"B","确定流水步距",{"key":19,"text":20,"correct":21},"C","分解施工过程，确定施工顺序",true,{"key":23,"text":24,"correct":14},"D","确定各施工过程的流水节拍数值","全等节拍流水施工也称为等节奏流水施工或固定节拍流水施工，是指在组织流水施工时，各个施工过程在各个施工段上的流水节拍彼此相等的流水施工组织方式。全等节拍流水施工组织第一步是将施工对象分解为若干施工过程，确定其施工顺序。 成倍节拍流水施工是指同一个施工过程在各个流水段上的流水节拍彼此相等，不同施工过程在同一施工段上的流水节拍之间存在一个最大的公约数，能使各施工过程的流水节拍互为整倍数。成倍节拍流水施工组织第一步是划分施工过程，确定施工顺序。",{"id":6,"name":27,"category":28,"favorite":29},"(初级)建筑与房地产经济","经济金融",0]