[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-49767":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},49767,53,1,"单选题","流水施工中的流水步距是指()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","某专业队进入各个施工段流水作业的持续时间",false,{"key":16,"text":17,"correct":18},"B","两个相邻专业队相继进入施工现场开始工作的最小时间间隔",true,{"key":20,"text":21,"correct":14},"C","两个相邻专业队进入施工现场流水作业的时间间歇",{"key":23,"text":24,"correct":14},"D","两个相邻专业队进入同一个施工段流水作业的搭接时间","流水步距是指两个相邻专业工作队相继进入施工现场开始施工的最小时间间隔，通常用“K”表示。流水步距的大小应根据需要以及采用的流水施工方式的类型经过计算确定。",{"id":6,"name":27,"category":28,"favorite":29},"(初级)建筑与房地产经济","经济金融",0]