[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-49765":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},49765,53,1,"单选题","最普遍的流水施工组织形式为()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","全等节拍流水施工",false,{"key":16,"text":17,"correct":18},"B","分别流水施工",true,{"key":20,"text":21,"correct":14},"C","成倍节拍流水施工",{"key":23,"text":24,"correct":14},"D","特定节拍流水施工","分别流水施工是指参加流水作业的各施工过程在各施工段上的流水节拍无特定规律的流水施工组织方式。在实际工作中，通常每个施工过程在各个施工段上的工程量彼此不相等，或各专业工作队的生产效率相差较大，导致多数流水节拍彼此不相等，而难以组织全等节拍或成倍节拍流水施工。此时，只能按照施工顺序要求，使相邻两个专业工作队在开工时间上最大限度地搭接起来，形成每个专业工作队都能连续作业的流水施工组织方式，称为分别流水施工或无节奏流水施工。它是最为普遍的流水施工组织形式。",{"id":6,"name":27,"category":28,"favorite":29},"(初级)建筑与房地产经济","经济金融",0]