[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-49762":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},49762,53,1,"单选题","某工程项目划分为 A、 B、C三个施工过程，各施工过程的流水节拍均为5天。若施工时分为四个施工段组织流水作业，且 B、C施工过程之间有3天技术间歇时间，则其流水施工工期为（）天。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","18",false,{"key":16,"text":17,"correct":14},"B","23",{"key":19,"text":20,"correct":14},"C","30",{"key":22,"text":23,"correct":24},"D","33",true,"考核流水施工工期的计算。T=（3+4-1）*5+3=33",{"id":6,"name":27,"category":28,"favorite":29},"(初级)建筑与房地产经济","经济金融",0]