[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-49758":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},49758,53,1,"单选题","某分部工程可划分为甲、乙、丙三个施工过程，其流水节拍分别为6周、12周和9周，若组织成倍节拍流水施工，其流水步距是()周。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","1",false,{"key":16,"text":17,"correct":14},"B","2",{"key":19,"text":20,"correct":21},"C","3",true,{"key":23,"text":24,"correct":14},"D","6","成倍节拍流水施工的基本特点：所有施工过程之间的流水步距都相等，且等于各施工过程的流水节拍的最大公约数。 （6 12 9 ）的最大公约数为3，也就是流水步距是3。",{"id":6,"name":27,"category":28,"favorite":29},"(初级)建筑与房地产经济","经济金融",0]