[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-49755":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},49755,53,1,"单选题","某专业工作队在一个施工段上完成一个施工过程的持续时间称为()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","流水步距",false,{"key":16,"text":17,"correct":18},"B","流水节拍",true,{"key":20,"text":21,"correct":14},"C","技术间歇",{"key":23,"text":24,"correct":14},"D","搭接间距","考查概念。",{"id":6,"name":27,"category":28,"favorite":29},"(初级)建筑与房地产经济","经济金融",0]